Process of Solid Wall Construction
1st Day: Steel Reinforcement and
Inspection
Each Steel Crew arrives at the job with the
proper equipment and necessary materials to complete the job,
eliminating deliveries or potential delays and waste on the job
site.
Inspection is completed.
The forms will be delivered and placed at
the job site by Superior Concrete Construction's Knuckle Boom
to maximize form setting efficiency.
2nd Day:
Form Panel Placement & Concrete Pour
A Panel Setting Crew will place the form panels
according to the blueprint, incorporating our state of the art
window bucks in that process.
Concrete is coordinated by our Company and
poured into the forms by one of our Concrete Pumps, eliminating
potential delays.
3rd
Day: Form Panel Removal & Clean-up
A Loading Crew
will then remove the forms from the set concrete walls, put in
baskets and then be removed from the job site by a Knuckle Boom.
Afterwards, mastic is applied to spreader ties. Houses are then
swept out and any trash removed.
This
1, 2, 3 Step process only requires one call from the job site
superintendent to Superior Concrete Construction and on call to
arrange the inspection.
On the
4th Day the project can be turned over to other trades to begin
their process.